INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Weirdness in Resource Usage View

Weirdness in Resource Usage View

Weirdness in Resource Usage View

(OP)
I have a series of tasks that are linked.  In the Gantt Chart view, I can clearly see the series of tasks starting a certain day, and the following tasks happening consecutively like I would suspect.

Now, the weird part:  When I go to my Resource Usage view, I see one of my resources working on item #3 in the list currently, and full-time.  Items 1 and 2 in the series have not occured yet, and this resource is assigned to all 3.  I go back to my Gantt Chart, and everything is fine.  The two views are contradicting each other, and the Resource Usage view is ignoring the links I set between the tasks.

Any ideas what might be going on here?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources