INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Retaining Wall Temp Steel

Retaining Wall Temp Steel

Retaining Wall Temp Steel

(OP)
Quick question.  Does Chapter 7.12 (ACI 318) apply to all flexural members for temp and shrinkage steel?  It uses 'structural slab' and says it does not apply to slabs on grade, but I wasn't sure about a cantilevered retaining wall.

Thanks

RE: Retaining Wall Temp Steel

Applies for cant. retaining wall.  Not for slab on grade. IMHO

RE: Retaining Wall Temp Steel

Some designers use a better quality mix, thicker slabs and closer control joints without any WWF or rebar in slabs on grade. The commentary to 7.12.1 says "the provisions of this section are intended for structural slabs only; they are not intended for soil-supported slabs on grade"

RE: Retaining Wall Temp Steel

You may want to also keep in mind the minimum flexural steel (not temp stl) at the tension face for retaining walls.

RE: Retaining Wall Temp Steel

Temp. steel  is to primarily control cracking. Generally it yield an unacceptable apperance. If the cracking acn be tolerated, then you dont need the steel. However, in terms of the overall structure, the cost of the temp steel is small.

RE: Retaining Wall Temp Steel

for retaining walls, I use chapter 14.3.  not 7.12.

RE: Retaining Wall Temp Steel

archeng59 is right for cantilever retaining walls.  We use chapter 10 for flexural design and meet 14.3.3 for horizontal temp steel.  Section 14.1.2 specifically states to do this.

RE: Retaining Wall Temp Steel

(OP)
Thanks for the info.  I didn't see chapter 14 until now.

RE: Retaining Wall Temp Steel

I believe that the requirements of 14.3 assume a joint spacing of 20 feet.  However, I can't find that provision anywhere in ACI 318.  Perhaps the 20 foot limit is just a rule of thumb.

RE: Retaining Wall Temp Steel

the Portland Cement Association (PCA) handbook, Building Movements and Joints, discusses the 20 ft joint spacing for walls with openings and 25 ft joint spacing for walls without openings.  I don't recall anything in ACI 318 about joint spacing, although I recall reading (don't remember where I read it) that the joint spacing should be based in part on the wall thickness.  

RE: Retaining Wall Temp Steel

ACI publishes ACI 350 for Environmental Structures (Tanks).  ACI 350 is very similar to ACI 318, but not for Temp/Shrinkage Steel (Tanks cannot leak).  ACI 350 Article 7.12 relates the required T/S steel to length of the wall between expansion joints: 0.3% for walls under 45 ft., 0.4% for walls to 60 ft., 0.5% over 60 ft.  I use this for all my walls.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources