INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Updating Suretrack program

Updating Suretrack program

Updating Suretrack program

(OP)
Hi, I am relatively new to Suretrack and am currently tasked with updating a monthly program. The original program was created on Primavera P3 and imported to suretrack for me to up date.

My understanding is that if I change the data date to the required date and then pres F9 to schedule the project then the project will automatically update and I can then adjust the individual tasks that require adjustment.

However when I schedule the revised program all the tasks are brought forward as id the data date was the new start date and everything is in the critical path as a result. Can anyone tell me what I am doing wrong?

Thanks in advance for any help you can give.

Cheers Mick

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.