INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Do i need to conduct a fresh PQRT?

Do i need to conduct a fresh PQRT?

Do i need to conduct a fresh PQRT?

(OP)
I have an existing PQRT with Single layer of Electro Slag Strip Clad applied on a 30mm thick Carbon steel plate. The PQRT meet all the specification requirement.

Due to Clients requirement (Client does not accept single layer technique) we have to give 2 layers. Hence the WPS is prepared with 2 layers.

Qualification as per section IX ASME is called for in the specification.

Now refering to QW 258.1 (Table) against 410.38 change  Multiple to single is shown in the table.

on refering to paragraph QW 410.38: In this paragraph " A change from multiple layer to single layer cladding/hardfacing, or vice versa" is given

Now the question is

1)which governs, is it the table or is it the paragraph?

2)That is do i need to qualify a fresh piece with two layers despite the fact that all the tests have passsed in single layer.

RE: Do i need to conduct a fresh PQRT?

bmoorthly,

1) it is the paragraph which governs, always. The table is but a short description of the paragraph.

2) yes you do need to requalify for double layer

Regards,

swig

RE: Do i need to conduct a fresh PQRT?

(OP)
Thanks a lotSwig

Is there a specified order of precedence given in Section IX (may be some where in forward or some where in general section), which states that paragraph governs or is it a common understanding.

RE: Do i need to conduct a fresh PQRT?

bmoorthy,

see QW-251.1

Swig

RE: Do i need to conduct a fresh PQRT?

I would concur, as well. Qualification of Welding Procedure Specifications follows the requirements for welding variables in QW-250. In QW-251.1 towards the end of that first introductory paragraph, “the Brief of Variables listed are for reference only”, and you need to refer to Article IV, Welding Data for specific information related to the variable.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources