INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Electrical Code

Electrical Code

Electrical Code

(OP)
I am installing 100hp air compressors.  I am wondering if I put the breaker panel within line of site from the compressors, can I eliminate the local fused disconnect at each compressor?  The breaker would be the point of lock-out.

Thanks.

CAF

RE: Electrical Code

I would say yes. Where is the starter?

RE: Electrical Code

The line of sight must be from the disconnecting means to the STARTER or control panel.  If this is a package system, I'm assuming the starter is located at the compressor skid.  

NEC also requires a local disconnect at the motor, but there are exceptions to this that you are probably aware of.  

NEC does limit "in sight" to 50 feet, regardless.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources