Smart questions
Smart answers
Smart people
Join Eng-Tips Forums
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Member Login




Remember Me
Forgot Password?
Join Us!

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips now!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

Join Eng-Tips
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.
Jobs from Indeed

Link To This Forum!

Partner Button
Add Stickiness To Your Site By Linking To This Professionally Managed Technical Forum.
Just copy and paste the
code below into your site.

bara1001 (Structural) (OP)
4 Jan 06 22:50
how often should rfive eigths rebar be tied in concrete
foundation wall   12inches vertical 12inches horozontal ?
Helpful Member!  boffintech (Civil/Environmental)
6 Jan 06 7:23
Concrete Reinforcing Steel Institute – “Placing Reinforcing Bars”

Wall Construction page 11-11

“The horizontal and vertical bars are wired securely to each other at sufficiently frequently intervals to make a rigid mat.  Tying is required depending on upon the size and spacing of bars, but not less than 3 ties to any one bar, and, in any case, not more than 4 to 6 ft apart in either direction”

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!

Back To Forum

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close