×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Pile Construction in Porous Rock

Pile Construction in Porous Rock

Pile Construction in Porous Rock

(OP)
I have a question about secant bored pile construction:

The secant piles (of 10-15m long) are supposed to be constructed in a layer of rock which is porous and low compressive strength. Another constraint is the water table is very high.

Does anybody know there is any method of keeping the borehole dry during concreting if bentonite is not allowed to use?

RE: Pile Construction in Porous Rock

I would expect the contractor to use augered cast-in-place, ACP, piles.  In this type of construction the pile is drilled and filled with concrete at the auger is removed.  Therefore, no bentonite or other drill fluid is needed.

RE: Pile Construction in Porous Rock

Real secant piles are executed with cased holes which should answer your question. Doing secant wall with CFA (  ACP in the US )is bad practice: the auger is too flexible and therefore your piles will be more tangent that secant, with the risk of leaving "windows" where materials + water could cave in during excavation.

RE: Pile Construction in Porous Rock

I agree "windows" can be a problem, however, depending on the soils and the quality of the contractor, ACP piles can be used to make very good walls.

I would say that for most contractors a 30 foot tall wall is approaching the limit for a high quality end product.

RE: Pile Construction in Porous Rock

(OP)
So, what is your solution....?

RE: Pile Construction in Porous Rock

Use polymer slurry instead of bentonite? Much better anyway to avoid cake build-up.

Why not use a pressure tremie that starts at the bottom.

RE: Pile Construction in Porous Rock

A dual-head drilling system, where the casing and the auger are counter-rotated would seem the way to go. If you use a CFA method (recommended) the hole will stay relatively dry and the concrete will be tremmied into the base of the hole during extraction. A hard/soft system would seem best - possibly with only the hard piles reinforced.(Maybe some nominal reinforcing in the soft piles.)

The casing "stiffens the drill string and limits bit wander.

I would be very careful using uncased secant piles to this depth. Very good drilling in an uncased hole would be expected to wander at least 1%. Therefore at 15m depth you should expect at least +/- 150mm wander from pile head. This results in the "windows" mentioned in previous posts.

On a recent project, we found a maximum horizontal wander of only 30mm between adjacent piles. This makes placing the walers a breeze, instead of cutting back, chocking and wedging. This was in sands overlying low strength sandstones.

Good luck.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources