hydrotest
hydrotest
(OP)
A quick heads up on Hydrotest. Looking for any approved methods that have test time <24hrs duration, suitable for large diameter onshore pipelines (test section length max 4km). Refs for standards or company approved methods would be usefull. Thanks.





RE: hydrotest
RE: hydrotest
Not UK based pipeline. Raised a related question to this on 21 Nov. Currently using Shell approved method but cold temperatures are really unforgiving for the allowable DP and data collection is almost untenable. The last test took 5 days - first two days pure stabilisation. I am interested how other people may of got round this and what approved methods/standards were used. This would really be test method for winter.
RE: hydrotest
This does not apply to PE pipe, which creeps and has a different regime, (also described in the document).
Hope this helps
StephenA
RE: hydrotest
B31-4 & API RP1110 the min. time for the Hydro. test is 4hours after stabilisation and pump is isolated.