INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ASME Sec. VIII : PWHT
2

ASME Sec. VIII : PWHT

ASME Sec. VIII : PWHT

(OP)
Is there any reference in ASME Sec. VIII to a specific number of thermocouples required during PWHT on carbon steel vessels or components? Thanks

RE: ASME Sec. VIII : PWHT

None that I aware of if you are putting the entire vessel in an oven.  On the other hand, if you are doing a local PWHT, there is specific guidance provided in WRC 452 that I would consider "good practice".

RE: ASME Sec. VIII : PWHT

Read UW-40 of Section VIII, Div 1. If you intend to perform a "batch" post weld heat treatment, thermocouples must be placed at specific locations to assure adequate temperature. The reference to this paragraph is UW-40 8 (c).

RE: ASME Sec. VIII : PWHT

That's right metengr - I should have checked out UW-40...  DOH!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources