INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Tower anchers, screw in

Tower anchers, screw in

Tower anchers, screw in

(OP)
Can any one tell me how much torque in FT/LBS does a screw in pile take to hold up a 96 ft free standing tower. I think I will use a 3 in. pipe with a 14 in. plate.Tower has 3 Legs 49 in. apart.  Would a person be wise to set the piles 8 ft. apart and frame them then set tower on top or just put them at 49 inchs apart.

RE: Tower anchers, screw in

tower22,

1) Get a structural engineer to analyze loads

2) Get a geotechnical engineer to give you recommendations for foundations in general and screw-in piles in particular.

Depending on the pile/anchor system and the subsurface conditions, the amount of torque could vary. Also, not all screw-in systems are created equal. You should consider load testing to ensure that the recommended solution works.

Jeff

Jeffrey T. Donville, PE
TTL Associates, Inc.
www.ttlassoc.com

RE: Tower anchers, screw in

(OP)
Thanks Jeff.
  WE are doing alot of sites. I thought if we set a 5000 ft/lbs of torque plus min. of 9 feet would work or do we need to analyze each site ?

RE: Tower anchers, screw in

tower22 - to analyze each and every site - that is always the golden question.  A lot depends on the geology of the area in which you are working.  There are many places where the basic soil conditions, say 1.5m or 5 ft below surface are remarkably the same over very large areas - bad areas are usually known.  Then there are sites where the conditions can change every hundred feet or less.  I would do a desk search of the geology of your area of interest; check out ag maps or US conservation maps for details.  Your geotechnical engineer should know if your alignment is "always good" - "often bad" or "this and that."  He would be able to help you arrange for a realistic programme of investigation.  In more uniform areas, you could space out the investigation, in poor areas, you may very well have to do an investigation at each site.  But get the geotechnical guy on board as part of your planning and I would surmise the overall design experience will be greatly enhanced.

RE: Tower anchers, screw in

When I worked in the power industry, the standard was to perform at least one soil boring at each structure.  If the structure was large, we did more than one.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources