INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Engineers Point to Flaws in Flood Walls' Design as Probable Cause of C

Engineers Point to Flaws in Flood Walls' Design as Probable Cause of C

RE: Engineers Point to Flaws in Flood Walls' Design as Probable Cause of C

The Times said:

"Yet in building the wall, corps officials acknowledge, they did not drive the steel pilings - the main anchors for the structure - any deeper than 17 feet.

This isn't quite right.  The steel in question was actually sheet pile cutoffs, rather than "anchors."  The Washington Post's interviews with members of the NSF investigation team referred to sheet piles that didn't cut off the seepage in the peat when the canal prism was cut deeper than the sheet piles.

The Times isn't ENR or the ASCE JGGE.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources