INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Grounding Underground Cable in Conduit

Grounding Underground Cable in Conduit

Grounding Underground Cable in Conduit

(OP)
To All -

   I would like opinions on clarifications on NESC rule 96C. Background : 7200V, single phase system, # 1/0 TRXLPE cable in 2" conduit, 60 Miles underground installation, service drop {transformer} approximately every mile.

   My question; Does NESC rule 96C apply to this situation with the requirements of (4) ground points every mile? Has anyone had similar situations / conditions?

Thanks

RE: Grounding Underground Cable in Conduit

Just for information what kind of installation is this. 60 miles is a long way.

RE: Grounding Underground Cable in Conduit

(OP)
Railway power for signal houses.

RE: Grounding Underground Cable in Conduit

Will you have pull points spaced between the transformers?

RE: Grounding Underground Cable in Conduit

(OP)
Yes, there will be pulling points, but the terrain and the plowing of the cable will dictate where those are. So, in essense I'm not able to predict where those will be. With that,  I'm looking for an interpretation to say how literal I need to follow the code.

Thank you,

RE: Grounding Underground Cable in Conduit

(OP)
In essense, yes that is correct. They mention every 1/4 mile because it is much easier to justify 4 grounds in every "running-mile". The question I have really, I guess, is : Is my situation relevant to this rule. Are there any distinctions made in the NESC between single and three phase distribution?

Also has anyone seen situations of plowing in cable-in-conduit, and not had any pull points at which to ground it. I forsee this as being a situation we may encounter at areas.

Thanks.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources