INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Modeling CB designed to overflow

Modeling CB designed to overflow

Modeling CB designed to overflow

(OP)
Currently working of a model with an existing catch basin with an 8" outlet.  I am trying to get the volume of water that will flow off site if the catch basin over flows.  Currently modeling the CB as a pond with a primary outlet for the pipe and a secondary outlet as the grate at the top.  The grate is set in the horizontal plan at the rim elevation. The flood elevation is also set to the rim elevation. Is this the correct way to model this?

Thanks,

RE: Modeling CB designed to overflow

Since the overflow will provide low head pushing out, I would remove the orifice flow constraint by modeling a broad crested weir with a length = to the higher of the frame's inside perimeter, or teh perimeter of the area at the grade break, if the inlet is sumped.  The breadth would be the width of that frame or grade break.

Make sure it is Secondary discharge, or the overflow will go to the device specified, or keep adding to the final outflow if Primary discharge is specified.

Remember: The Chinese ideogram for “crisis” is comprised of the characters for “danger” and “opportunity.”
-Steve

RE: Modeling CB designed to overflow

The key is to determine what will control the overflow.  As LHA suggests, the CB overflow is often modeled as a weir.  In some cases this may be at the rim of the CB, but in other cases it may be a higher low-point in the surrounding pavement.

If the control point is above the rim, you may also want to define the additional above-grade storage (as part of the CB/Pond) since it can have a significant effect on the hydrograph routing.

For further details please see www.hydrocad.net/pipes.htm

  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources