INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Preconstruction Surveys

Preconstruction Surveys

Preconstruction Surveys

(OP)
I'm looking for information on how to conduct a preconstruction survey. There are several "tired" foundations nearby our pile driving operation and I would like to limit our liability by taking some photos, video, and measuring some foundation cracks.

We will be monitoring vibrations during construction. Any helpful hints or links to relative information on how to conduct such a survey and an example of a survey would be great.

RE: Preconstruction Surveys

Hire a professional who does these as part of their normal business.  Surveys should be conducted by a third party when possible.

The best source for preconstruction surveys for pile driving and rock blasting is a book by Lewis Oriard: The Effects of Vibrations and Environmental Forces.  Available from the International Society of Explosives Engineers.  www.isee.org.

Frank Lucca M.I.Exp.E.
www.terradinamica.com

RE: Preconstruction Surveys

GOTEK...I agree with Explo.

Third-party evaluations protect you better.  They are done by prescribed methodologies (usually your DOT will have a procedure since they get accused regularly of causing distress to adjacent properties).

RE: Preconstruction Surveys

(OP)
Ron & Explo,

I appreciate the response, my problem is we are the DOT and we don't have a procedure. I basically am followig guidance given in one of Charles Dowding's texts. I wholeheartedly agree that a third party is best to eliminate bias...but since the third party(s) has consistently yielded fuzzy video, poor audio and incomplete survies we have not done well in the legal system or in the realm of public opinion. Now you're probably saying that there is a performance issue with our Contractor or the very least his Subcontractor and even perhaps our DOT Construction engineer - I would be the first to agree. So, we have taken soem steps internally to protect our liability...video, photos, and documentation - I believe - will go along way in limiting our liability and enhancing our customer relations.

RE: Preconstruction Surveys

I used to work with David Miller and now he has his own firm that does just what you are needing.  Contact him as provided below to see what he might recommend...


David K. Miller, P.G.
President
http://www.seismicsurveys.net

RE: Preconstruction Surveys

I agree it is good to have third party, but you should also do horizontal and vertical suvey with good control. Good control can be a tricky thing on a vibration monitering project. Be sure to tie to cotrol sufficently away from the work. Another trick is to fill the cracks with plaster of paris. The plaster will not shrink, so if you see a gap, the crack is opening. Since it has low compressive srength, it will crush if the crack starts to close

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources