INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Dozing production

Dozing production

Dozing production

(OP)
If I doze a heap of X cubic meters for 30 meters from A to B. I then doze the same material from B to C for 30 meters.
If it takes me 1 hour to do all this job what is my production per hour? Is it X cubic meters or X times 2?
why ?
I am aware of factors that need to taken into account when calculating.

RE: Dozing production

Your productivity is X cubic meters/hr.  Why?  Because you've moved X cubic meters over a distance of 60 m in the course of 1 hour.  Only the time to complete the total cycle matters, not each stage.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources