INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

EVMS

EVMS

(OP)
anyone have experience using one of the programs employing EVMS strategies?

which programs?

RE: EVMS

I take it EVMS is an acronym for Earned Value Management Software, or something similar?

The organisation that I work for uses InControl. You can enter progress, as percent complete, at the deliverable or WBS-element levels and it calculates all the earned values and performance indicies.  It pretty good once you get to know your way around the software.

RE: EVMS

(OP)
yes on the acronym and thanks for the reply.

RE: EVMS

Primavera has a bunch of papers on it posted to the website. Basically as I understand it, you assign costs and revenues to your activites and as you update your percent complete, you can determine your profitability or lack there of and compare it to a base line schedule. Not a bad idea but not the rocket science it is made out to be.

RE: EVMS

Agreed with DRC1 that earned value management is really pretty simple.  It can easily be done on a spreadsheet.

Inputs:
Budget at Completion, BAC    
Actual Cost, AC
Planned Value, PV
Percentage Complete, PC
Estimate to Complete, ETC

Outputs:
Earned Value, EV = BAC x PC    
Cost Variance, CV = EV - AC
Percent Cost Variance, CV% = (CV/EV)%
Cost Performance Index, CPI = EV/AC
Schedule Variance, SV = EV - PV
Percent Schedule Variance, SV%, = (SV/PV)%
Schedule Performance Index, SPI = EV/PV
Estimate at Completion, EAC = AC + ETC    
Variance at Completion, VAC = BAC - EAC
Percent Variance at Completion, VAC% = (VAC/BAC)%
To Complete Performance Indices        
- To achieve BAC
  TCPI = (BAC - EV)/(BAC - AC)
- To achieve EAC
  TCPI = (BAC - EV)/(EAC - AC)

The estimate to complete can also be calculated independently:
- Future performance influenced by past cost performance
  ETC = (BAC - EV)/CPI
- Future performance influenced by past cost performance (80%) and schedule performance (20%)
  ETC = (BAC - EV)/(0.8*CPI + 0.2*SPI)
- Future performance influenced by previous three CPI results
  ETC = (BAC - EV)/(CPI1 + CPI2 + CPI3)/3
- Future performance influenced by past cost and schedule performance
  ETC = (BAC - EV)/(CPI*SPI)

RE: EVMS

(OP)
thanks for the replies.  

i read a white paper on it and how it aides in compliance with S-Ox sec.404.

but i also agree with DRC1 and dbuzz, it is not PHD material!

RE: EVMS

One shortfall of EV is that it assumes that costs proceed lineraly with % complete, i.e te cost to perform 20% of the work is half of the costs to complete 40% 0f the work and a quarter of the cost to complete 80% of the work. In actuallity (at least in construction) it is rarely linear. Generally the first 20-25% involves some setup, learning curve and similar problems. The middle (hopefully)goes well and the last 20% falls off due to having fewer units to employ resources against, cleanup and dimantling and corrective work on previous units. In the end, the average should be close to the actual production rate. However, projecting costs to complete off the 20% completion mark may give a very conservative answer.

RE: EVMS

DRC1, I respectfully disagree.  Earned Value doesn't assume that costs are incurred linearly on a project.  Instead, Earned Value is a performance measure for comparison against the Actual Cost and the Planned Value.  The Planned Value is almost always plotted (time-v-cost) as an S-curve, with a flatter gradient at commencement and completion, precisely for the reasons you describe above.

RE: EVMS

I stand corrected. I guess if you took the time to use an proper curve for the planned value, it would be pretty slick. I have only seen it used with a linear proportion for planned value and hence my lack of enthusiasim. However, if you were to look at the Planed Value predicted in a realstic manner, I bet that would give interesting (and useful) results.

RE: EVMS

There must be some S-curve equations out there that you could use in a spreadsheet EV solution.

I'll see if I can find some.

RE: EVMS

As a matter of further study if you use MS Project or P3 you can look at resource loading the schedule and then querying the progress.  The baseline schedule will generate the planned value curve and you can plot the earned value curve against it to confirm winning or losing.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources