INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Relief system piping

Relief system piping

Relief system piping

(OP)
I have space constrain on a relief platform which has a lenght of 6000mm,i want to carry out piping layout of the relief system which has an 8" 900#RJ ristriction orifice which is placed inbetween a 10" ball valve and an 8" ball valve.I have to  considered the straight run reqiurement of 7930mm upstream  and 1270mm downstream of the risriction orifice.What do you recommend

RE: Relief system piping

Look into using straightening vanes. Straightening vanes are installed in the upstream section of meter tubes to reduce flow turbolence. Installed upstream of flow meter when adequate upstream pipe run section can not be met their use often allows sufficient reduction of stream meter tube lenght.

http://www.emersonprocess.com/DANIEL/Products/Liquid/accessor/Vanes/ds_sheets/Straightening%20Vanes%20Cat%201100%20363KB.pdf

David Baird
mrbaird@hotmail.com
Sr Controls Designer
EET degree.
Journeyman Electrician.

RE: Relief system piping

I'm confused what you are asking about regarding an orifice, upstream and downstream distances and a post titled "Relief System Piping"

RE: Relief system piping

(OP)
TD2K,
The ristriction orifice is a flow measuring instrument installed on the  process line and my job notes stipulates a pipe striaght run before and after the orifice should have a distance of 7930mm  and 1270mm.This arrangement is part of a relief system ,that was why i posted it  with that title.
Hope this will help to clerify the quetion.  

RE: Relief system piping

It seems like you're describing installing an RO in the relief path / flare system.

It's just not done - especially if you're describing an 8" plate with a much smaller orifice in it.

Do I have it wrong?

RE: Relief system piping

adeboy,
The straight run length should depend on the beta ratio of your orifice.

If you really require the more run length, you should arrange the piping.

RE: Relief system piping

adeboy,
I assume you mean Orifice Plate Meter when you refer to the RO? If so are you metering gas? If so is it indicative or is it fiscal metering?
Maybe I'm barking up the wrong tree but if it is fiscal gas metering you should look in your project nominated standards, if it mentions ISO 5167 then there are tables for minimum lengths of straight pipe based on factors such as the number of bends in the pipe prior to the meter run, and the orientation of the bends. Using a flow conditioner, either a tube bundle as mentioned by David Baird, or a flow conditioning plate, will allow you to reduce straight lengths.
Check your design/project standards to see what you need to comply to.
Justin.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources