INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

API 650 Anchoring

API 650 Anchoring

API 650 Anchoring

(OP)
I have a tank with a design pressure of 4 oz/in2. The tank will have an Emergency PSV installed meeting API 2000 venting requirements. In determining the need for anchors is it necessary to still consider the uplift due to failure pressure when there is no uplift during a venting?

RE: API 650 Anchoring

As far as I can tell, yes.

As another post a while back pointed out, it appears that Footnote "a" in Table 3-21b of API-650 should refer to F.1.2, instead of F.1.3, if that helps.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources