INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

hydroseeding steep slope

hydroseeding steep slope

hydroseeding steep slope

(OP)
Steep slopes ( angle %37 maybe more) major soil type coarse material and topsoil deep 5 cm. no B horizon.

hydroseeding. my question is hydroseeding application hows working on this slope. if is no topsoil how I can paste seed to surface.

RE: hydroseeding steep slope

Call a Hydroseeding contractor and gp watch a few applications.

RE: hydroseeding steep slope

Shouldn't be much problem, you're still less than 2H:1V, but you will likely want to install some erosion control matting.  You could also consider a "bonded fiber matrix" which is like a spray on hydroseed+mat combination, one such product is Soil Guard.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources