INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Marshall Value for Binder

Marshall Value for Binder

Marshall Value for Binder

(OP)
I am currently involved in the paving portion of a large commercial project. The Marshall Value for the binder that has been forwarded to me by the asphalt lab is 168.7 lb/cf. This seems incredibly high to me, as the highest dry value I have ever measured was around 150. I have requested the mix design, but I'm still curious as to whether any of you have encountered values this high.

RE: Marshall Value for Binder

It does seem high - we have values of 2.65 g/cc here but our specific gravity of the coarse aggregate approaches 3 (2.95 to 3.05).  This is the only way I can see how your Marshall Density is so high.  Or, perhaps, they have given you not the Marshall Density but the Rice Density (maximum theoretical density) - usually taken as 104% Marshall = 100% Rice.

RE: Marshall Value for Binder

SCGeo...I agree with BigH...awfully high.  Even if your Rice value is high, I wouldn't expect that much.

In your area (assuming "SC" means the Palmetto state), coarse aggregate specific gravities will vary from a low of about 2.45 to a high of about 2.70.

One thing you might look out for is that someone is using steel slag as coarse aggregate in the asphalt (you have a producer in Georgetown).  Steel slag has a highly variable specific gravity.  Not a good idea because of the instability and potential destructive expansion of steel slag, but it has been done and the mistake often repeats itself every 10 years or so!

Get the mix design.  I can't imagine a producer having a mix design with a density that high....tough to get compaction if its wrong!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources