HVAC loads in offshore project
HVAC loads in offshore project
(OP)
Does anybody know what percentage of loads in the entire offshore project nomoally?
When was the last time you drove down the highway without seeing a commercial truck hauling goods?
Download nowINTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
HVAC loads in offshore project
|
RE: HVAC loads in offshore project
63.67284635 percent!
Just kidding but really,
Yah gotta give us more information... I can think of a dozen different "offshore projects".
RE: HVAC loads in offshore project
You have to give more detailed informations on the layout of the "offshore platform".
Usually the load percentage is about 50-60%. And you have to bear in mind the maintenance issue, i.e. units out for service and what the load is compared to n-1 or even n-2.