UM vessel and partial data report
(OP)
If have the following question:
Do I need a partial data report (signed by a autorised inspector) for a pressure containing part of a UM-marked vessel if produced by another factory?
Or is it sufficient to test the part again in our shop and stamp it with our ouwn UM stamp?
Do I need a partial data report (signed by a autorised inspector) for a pressure containing part of a UM-marked vessel if produced by another factory?
Or is it sufficient to test the part again in our shop and stamp it with our ouwn UM stamp?





RE: UM vessel and partial data report
RE: UM vessel and partial data report
I understand that you can not sub a UM vessel,
but on the othe hand: your shop is responsible for the mfg of the vessel and you could get away with a partial certification from another mfr.
You could get away but just be carefull because if your AI does not endorse the practice, you will loose the recertification at yearly audit. I am sure of that.
You better consult your AI (he still involved in your UM mfg and can review and INSPECT whenever he/she wants to)
ER