INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Pressure vessel attachments

Pressure vessel attachments

Pressure vessel attachments

(OP)
I would like to know if it is acceptable for a pressure vessel, designed and built according to ASME VIII div 1 to be directly welded to the incoming & outgoing piping instead of flanged connection. I am discussing with a contractor who suggets to weld the piping directly to the vessel nozzles. The system is designed for power piping carrying steam at around 90psig - piping design is to B31.1. Comments appreciated. Thanks

RE: Pressure vessel attachments

markzu3,
         There is no problem connecting the pipe to the pressure vessel using a welded connection. Obviously the materials of the pipe and branch need to be comparable for welding process.

RE: Pressure vessel attachments

Agree with DSB123. Also you need to evaluate piping loads on the nozzles to assure adequate design with Code requirements.

RE: Pressure vessel attachments

markzu3-

No problem at all. Not frequently done, but often enough. For Code references, see VIII-1 U-1(e)(1)(c) and UW-13(g) and Fig. UW-13.4.

The VIII-1 scope ends at the weld prep of the nozzle. The weld metal is piping code (in your case B31.1) territory. This makes sense, as it makes shop fabrication and stamping of the vessel possible. If the weld metal was in VIII-1's scope then the field weld to attach the piping to the vessel would have to be completed prior to putting the U stamp on the nameplate etc.

jt

RE: Pressure vessel attachments

mark,

I agree with those above

Not a problem.....the specification of vessels with butt weld ends is common.

However, the possible removal/replacement of that tank or vessel may be a problem in the future....

MJC

  

RE: Pressure vessel attachments

I see a problem with the practic,
of who will take responsability for the vessel and who will for the piping,
the piping contractor can verywell do the weld directly to the vessel,
the vessel stamp ends at the first flange or last welded connection and that one can be a nozzle, pipe stub end but not a direct vessel component as SE head or shell.
I like to hear other coments. If the vessel mfr takes responsability, then that Co. will have to weld the pipe whether at the shop or field if the stamp covers both.
I believe the piping contractor is not authorzed to touch the vessel in that regard.
er

RE: Pressure vessel attachments

In my opinion, pressure vessel should be provided with flanged ends. What about the hydrotest of vessel? How we will carry out the hydrotest of vessel.

RE: Pressure vessel attachments

GenB-

I think we're violently agreeing here. I don't think anyone has advocated welding pipe directly to the shell or heads. The vessel fabricator provides a nozzle neck with ends beveled/prepped for welding, as though the fabricator was going to weld a weld neck flange on. Except the flange is not installed; the piping contractor in the field simply does a field weld of the nozzle stub to the piping.

PEHasan-

It's done often enough and fully complies with the code. Hydrotesting is simple: If I ask for a 12" stub, you install a 14" with a 2:1 head (chances are that we're talking about a large pipe here). After the hydro you cut the nozzle to length and prep the edges for me. Simple.

jt

RE: Pressure vessel attachments

Apparently some states charge a penalty for each flanged connection in a plant.  Presumably because it's a potential leak source.

RE: Pressure vessel attachments

I believe this would require an "R" stamp, as you are welding directly to the vessel.

RE: Pressure vessel attachments

jt,
violent enough,  you are right I did not see the stub in the orig posting,
it is a standard procedure to buttweld piping to an incoming nozzle,.
bye, er

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources