INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

new and existing pad footings to existing structure

new and existing pad footings to existing structure

new and existing pad footings to existing structure

(OP)
hi, structural modifications have to be done to accomodate 3 new floors above an existing 5 storey building. I am unfamiliar with working with existing strucures and a few queries as to the best options of work method, replacement and connection etc. suitable for the situation.

-the placement of new pad footings 1.8x1.8.0.7 to new columns, founded 1.5m below ground slab level.

-some existing pad footings 2.4x2.4x0.9 founded at 1.5m have to take additional loads. Suitable increased bearing capacity is at a depth of 2.1m or increase in pad size to 3.6x3.6.

-how the columns can be connected to the underside of existing beams and if they should be reinforced concrete or composite. (the existing building is steel framed and encased in concrete for fire protection )

- How the exsiting columns can be best removed.

RE: new and existing pad footings to existing structure

Selr,

First, get your geotech to help you out.

Based on your description of the problem(s) it seems that you want to
1)add new columns and square footings below an existing slab.
2)modify the foundations for existing columns.
3)connect the new columns to existing beams - presumably these beams support the existing floors above the slab grade.

1)Without knowing the exact situation, you will probably need to demo portions or all of the floor slab to excavate for the new foundations.

2)For modified foundations, you have some opportunities and some problems. First, you need to decide if you can safely support the column loads while you are mucking about with the column's foundation.

If not, you may want to look at using micropiles to bolster the foundation capacity without having to remove the existing foundation. There are a number of micropile contractors out there that will be able to tell you what is going to be involved in the process (Hayward-Baker, Nicholson).

If you can support the column temporarily, then you need to decide if you want to go to the trouble of shoring the excavation, (possibly) demolishing the existing foundation and constructing the new one. Depending on the number of colums that will need to have modified foundations, this could be a little tedious.

3)Is outside my realm of professional experience.

Good luck!

Jeff

Jeffrey T. Donville, PE
TTL Associates, Inc.
www.ttlassoc.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources