INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Any Planner/Schedulers in this forum

Any Planner/Schedulers in this forum

Any Planner/Schedulers in this forum

(OP)
Yes I am aware this is cmms forum but too me they go hand and hand. I am looking for direction in after pulling new request out and bringing to weekly meeting where do i go from there? ex meeting begins synopsis from there..

RE: Any Planner/Schedulers in this forum

I'm not sure what you are asking.  Could you please clarify.  Typically, a work order process would be to:
- supervisor review work request
- goes to planner where planner can review past wo's for this problem, scope out repair, write up tasks, order parts, etc.
- work scheduled & issued to craft
- work completed
- completed work reviewed against planned work to gauge accuracy of planning
- completed work entered into work history

RE: Any Planner/Schedulers in this forum

(OP)
that was very good and answered a couple of questions also.

RE: Any Planner/Schedulers in this forum

It is very clear description of the planning workflow. I would just suggest separating planning from scheduling. When planner does the planning, WO should go to schedulers' pool. The same person can do actual scheduling, but it is different activity.

Simply after planning is done, normally WO cannot be scheduled immediately if it is not top priority. (If you can schedule all the work immediately, that normally clearly shows that you have too overcrowded workforce!)

The sole scheduling system should be based on logical and mutually agreed priority system, and routinely developed workload charts/tables for job dispatching.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources