INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

EBQ processing determines the cost

EBQ processing determines the cost

EBQ processing determines the cost

(OP)
Hi,

Our MRP system is set the way that the EBQ defines the cost of the part. But since we do not have an annual demand...(we do not have standard orders for manufacturing) can anybody suggest a way to use EBQ?

Mechanical Engineer

RE: EBQ processing determines the cost

EBQ?  Economic break-even quantity?

Griffy

RE: EBQ processing determines the cost

Do you mean EOQ, economic order quantity?

RE: EBQ processing determines the cost

(OP)
I mean Economic Batch quantity..for production

Mechanical Engineer

RE: EBQ processing determines the cost

MRP systems are planning systems and are not the cost setting mechanism in any plant I've worked. The BOM and labor standards are the cost setting mechanism.

In today's lean thinking world the goal is to have the batch quantity equal one. This is not to say all batches equal one but to force setup times between jobs to be reduced to as low as possible.

Batch quantities may also be based on other criteria than setup time. One piece of raw material such as one length of barstock makes 10 parts. Instead of storing a partial bar the batch quantity will equal one complete piece of raw material.

The real problem of EOQ or as you call it EBQ is the over-production of parts which you may not ever use.

RE: EBQ processing determines the cost

It seems you are manufacturing spare parts so you cannot use typical planning close to just-in-time when you have known customer or on the other hand marketing-based planning?

I know about use of what EBQ just for that, spare parts, because in that case you can use some statistic and models to predict demand, but only decision that you make in agreggate planning is just that, which EBQ to use; it is the reason why it is set as a variable in some calculating systems.

RE: EBQ processing determines the cost

hisrik,
Economic order/batch/lot sizing assumes that you have some yardstick to measure against.  It may be competitive pricing, process cost goals or process comparison. It can be used to compare costs to market information but is irrelevant without the comparative factor.
Our mrp system allows the use of EOQ for generating order quantities but until the Great CFO/Beancounter issues a Rule for Comparison we will not use it.

Griffy

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources