INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Pressure Vessel: Div. 2 replacement by a Div. 1 Vessel

Pressure Vessel: Div. 2 replacement by a Div. 1 Vessel

Pressure Vessel: Div. 2 replacement by a Div. 1 Vessel

(OP)
Hello:

From reading the discussion board, this seems to be a great place to learn more and have questions answered.  I look forward to interacting with all of you!

Now my question...:)

I am in the process of replacing a Div. 2 Vessel with a Div. 1 Vessel.  Has anyone done this?  If so, any idea on the cost it would take to accomplish this task?

Thanks in adavance!

Chalo

RE: Pressure Vessel: Div. 2 replacement by a Div. 1 Vessel

If you have not done so already, you should review ASME Section VIII, Div 2 Article G-1, paragraph AG-100 (2)d thru e.

RE: Pressure Vessel: Div. 2 replacement by a Div. 1 Vessel


  The decision is a tecnico economical mater.

For small vessels  the steel savings that you can get when selecting the Div 2, do nor pay the 100% radiography and the additional engineering cost.But in a bigger vessel loke  400 m3, you can save nearltyy 30 % of the steel and can be wortwhile.

RE: Pressure Vessel: Div. 2 replacement by a Div. 1 Vessel

Team Members

ASME SECTION VIII, DIVISION 2, is in rewriten using CODE

CASE 2268-1 Jaunary 1, 2004,
Aleenative Ruel for Determining Allowable Ecternal Pressure and Compressive Stresses for Cylinders, Cones, Spheres, and Formed Heads Section VIIi, Division 1 and 2.

RE: Pressure Vessel: Div. 2 replacement by a Div. 1 Vessel

Huh?

RE: Pressure Vessel: Div. 2 replacement by a Div. 1 Vessel

SPLIT:
The 30% saving in steel cost is history. The safety factor of Div.1 allowable stress was reduced from 4 to 3.5 in the year of 1999. Compared to S.F. of 3 of Div.2, the difference is only about 15%.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources