Estimating Site Work
Estimating Site Work
(OP)
Hello, I'm new to this site and there seems to be a wealth of info here. I was wondering if there is any general rule of thumb for estimating grading/site prep, etc..? I know that every site is different and it depends on numerous factors, but is there any general rule? The reason I ask is that I have a 6.5 acre site that a local church is interested in buying from me if it were pad ready. I know there are many more factors that need to be taken into account, but suppose no dirt needed to be hauled in/out, no retaining wall, etc... Am I talking $300k, $1M,? Is there a general price/acre?
Thanks
Thanks





RE: Estimating Site Work
If he says he needs some type of plan to go by, then talk to a local engineer. I know where I'm from it's pretty hard to go out and prepare a pad such as that without getting local approvals anyway.
RE: Estimating Site Work
RE: Estimating Site Work
As far as earthwork goes:
These numbers are a few years old, but these were good prices at the time:
Strip and pile topsoil : $1.50/cu. yd.
Move cut/Fill : $1.00/cu. yd.
place/compact fill : $1.00/ cu. yd.
clearing trees : $1k/acre
grubbing: $1.5k/acre
These numbers don't do you much good unless you have some idea for existing and final contours or elevations
I would maybe add to your final number based on these estimates an increase of 10% due to inflation, fuel prices, etc.
A rule of thumb for commercial work is $3000-$3500 per parking space.
Of course, these numbers don't include sewer, water, erosion and sediment control measures, road work, power, permits, etc.
Depending on what part of the country you are in and the existing topography, site work can be one of the largest sources of project over runs.