×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Minimum Pile Length

Minimum Pile Length

Minimum Pile Length

(OP)
Does anyone have a good reference for minimum pile lengths for HP steel piles driven to refusal on limestone bedrock?  The piles are only loaded axially.  For PADOT, the minimum allowable pile length is 10 feet.  I have used 6 feet in the past with success but that was based on my "gut" instinct and not "hard" science.  I am looking for a reference that will explain why there is a minimum pile length.  I am assuming it is based on pile driving stresses or lateral loading but am not sure.

Thanks  

RE: Minimum Pile Length

I am not exactly sure of the answer since it has been a long time that pile designs have actually been given to me. However, in foundation engineering, I did study that if the piles are designed as friction piles, then the length should be at least 5 times the pile diameter - any length less than that the soils tend to move upwards and the entire skin friction is not generated in this length.

For end bearing, the socket length should be at least 2 to 3 times the pile diameter. I think both the conclusions are based on field tests.
Rgds

RE: Minimum Pile Length

ashjun, what is the "socket length" of an end bearing pile?

RE: Minimum Pile Length

If the piles would be that short, why not just use a footing?

RE: Minimum Pile Length

I would consider using poured in place concrete plies.

RE: Minimum Pile Length

hi, socket length is the length of the pile embedded in rock or refusal strata.
Rgds

RE: Minimum Pile Length

I'm not sure how you can get a socket length in rock for a driven pile.  You may be able to drive the pile slightly into rock, but probably not enough to consider it a socket.

I would not be surprised if the minimum pile length was based on economics in comparing the cost of additional driven pile length versus extra excavation, concrete, and backfill required to build a spread footing at a deeper elevation. Maybe someone calculated that a footing with 10 feet maximum of extra depth would be cheaper than driving piles for a shallower footing.

RE: Minimum Pile Length

It seems to me that the "minimum" length in the original post is not a theoretical minimum based on soil/rock mechanics principals but based on common sense construction considerations.  They must figure that anything less than 3 m could have had another system used that would make more economic/construction sense.  Seems expensive to bring in a pile rig for a lot of 7 footers!  Excavation to the 7 or 8 ft, set footing, etc. might be a whole lot more appropriate.

RE: Minimum Pile Length

BigH,

I guess great minds think alike.  We responded within 11 seconds of each other with essentially the same answer.

RE: Minimum Pile Length

OPEinc - and from across the world!!

RE: Minimum Pile Length

Hi again,
Yes, it all depends upon the minimum cost, the availability of equipment and the experience of the local engineers amongst other factors.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources