INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Elongation of Post Tension Cables

Elongation of Post Tension Cables

Elongation of Post Tension Cables

(OP)
Our builder 'forgot' to call the Post-Tension CO to test the cables in our foundation for elongation.
The PT CO just did a final stressing, even overlooking one cable completely.
Should the PT CO have gone ahead, as they did, and done a final stressing without an elongation measurement and report?
We also know that the foundation pad was not prepared correctly, and there was no site preparation plan.
We are experiencing much differential settlement and damage to our home.  Are there any other problems we may encounter over the years of our 6 year old house?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources