Task predecessor based on day of week
Task predecessor based on day of week
(OP)
I have 2 task A,B. Task A is a random day that is usually forced on me one way or another. Task B is always the 1st Tuesday after Task A. Is there a way I can set up the predecessor for Task B to be the proper Tuesday date? Thanks.





RE: Task predecessor based on day of week