INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Full pen weld on butt joint of tube

Full pen weld on butt joint of tube

Full pen weld on butt joint of tube

(OP)
I need your guidance:

I have tube steel that needs to be jointed at a splice point that requires full pen welding. I must develop the joint.

AWS does not provide a pre-qualified full pen joint. I am asking that the welder must be a 6GR qualified/certified. Do I need also have qualified for new joint? If so, what is the right verbiage to put on the plans?

Regards,

Lutfi
www.cdeco.com

RE: Full pen weld on butt joint of tube

More than likely he will.  First we need the code or standards you are working under.
You have part of it covered but we need more information as to sizes and materials of the tube in question and if possible the thickness the welder would or has qualified to.
If we know your tube sizes we can specify what qualification the welder  has to have.

RE: Full pen weld on butt joint of tube

(OP)
The tube is 12X4X1/4.

Lutfi
www.cdeco.com

RE: Full pen weld on butt joint of tube

If you are involved with structural steel applications, you need to obtain a copy of the 2004 Edition of the AWS D1.1 Structural Welding Code-Steel. All of the information is contained in this code regarding weld procedure qualification and welder certification. This code should be referenced on any drawings or specification for this job.

RE: Full pen weld on butt joint of tube

Per ASW D1.1, 3.13.3 (2), "There are no prequalified joint details for CJP groove welds made from one side without backing"

You can make the butt joint with backing using a "prequalified joint" WPS.

RE: Full pen weld on butt joint of tube

(OP)
Thanks for you the help.

I actually was reading the right AWS section 3.13.3, however, I misread it.

I can make a full pen joint with welding being done from one side and use backing bar. I will require the joint to be tested using magnetic particle.

Thanks,

Lutfi
www.cdeco.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources