INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

pullout capacity of grouted pier/pile in rock

pullout capacity of grouted pier/pile in rock

pullout capacity of grouted pier/pile in rock

(OP)
How would you estimate the pullout capacity of a grouted pier or pile in drilled rock?

Thanks.

RE: pullout capacity of grouted pier/pile in rock

First figure the skin friction capacity of the pile just like you would for a downward load.  Then you need to look at the joint pattern of the rock versus the depth of embedment of the pile into the rock to determine if the rock will tend to break/separate on joint planes that are smaller than a typical pullout cone.  Then look at the weight of the smallest pratical pullout cone versus the uplift (pullout) capacity that has been calculated.  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources