I am currently designing a 40-feet high single story warehouse type concrete building (Seismic Zone 4). The roof system is open web joist and metal deck (no concrete). I am designing the wall anchorage to the diaphragm at the roof level for the walls running parallel to the open web joist. What details are typically used and analyzed?






RE: Wall Tie
Some engineers also put in extra steel members in the plane of the diaphragm at this area to make sure the roof panels won't crush from the force coming in perpendicular to the wall.