INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

structural fee as percentage of total arch. fee

structural fee as percentage of total arch. fee

structural fee as percentage of total arch. fee

(OP)
What is a good budget number to use as a percentage of a typical architectural fee for the structural portion of the job?  For example, a shopping center, school, office building, etc., where the total architectural fee is around 6 to 10% of the construction budget.  I have found that in the past about 10% of the total fee is about right, but with the IBC 2000 requiring a more stringent design for seismic, has the structural fee gone up accordingly?

RE: structural fee as percentage of total arch. fee

MikeE55,

Our firm typically bases our fee on the total construction cost which is normally between .75% and 1% depending on the size and complexity of the structure. We also increase our fee by 10% if the Seismic design catagory is D or worse.

Regards,

AUCE98

RE: structural fee as percentage of total arch. fee

I've seen lots of variations through the years but here are a few common ones:

1.  Structural fee = 3.0% to 3.5% of the STRUCTURAL portion of the project.  Thus, the contract is written with the Architect to have the contractor provide a breakdown of the portions of the project and the fee is then calculated from that.  Normally, the structural portion of the construction cost for most buildings varies between 20% and 35% of the total - but this varies a lot depending on site costs, finishes, etc.

2.  Structural fee = 0.75% to 1.0% of the total construction cost.  The exterior site costs are usually excluded from this calculation.  Means uses 1% to 2.5% for projects - I think the high end 2.5% is for more pure structural projects where there is less finish work, etc.

3.  Structural fee = 17%-20% of the total A/E fee.  This is from a group called Zweig-White who do studies on fee breakdowns throughout the USA.  

RE: structural fee as percentage of total arch. fee

I agree with AUCE98 and JAE,  I think all structural engineering fees depend on where the job is located.  Here in the midwest the fees might be a little less because we are not dealing with coastal winds and siesmic loads.

I would be a rich man if I could get more that 1.0%!!!

RE: structural fee as percentage of total arch. fee

Lutfi,

Just to explain a little further, the majority of our work is in the laboratory and research facility field, which causes the construction cost of these buildings to inflate due to the amount MEP equipment in the structures which works out well. I would also agree with joemarch that fees are fairly regional.

Regards,

AUCE98

RE: structural fee as percentage of total arch. fee

I agree with the all what have been stated. I am fully aware of the cost of MEP equipment which can be substantial with minimum relation to design effort, structurally speaking.

Regards,

Lutfi
www.cdeco.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources