INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Camber for two way slab

Camber for two way slab

Camber for two way slab

(OP)
Does anyone have any guidelines for the determination of camber for a two way slab. I have seen it done but I have not personally done it. I cannot find it in a code or any other reference that I had. I would have thought that the long-term calculated deflection value would be suitable at mid-slab.

RE: Camber for two way slab

It depends on what you want the precamber to achieve.

Is there brickwork or other brittle finishes that will be damaged by deflection of the slab. In this case precamber will do nothing to reduce the deflection experienced by the brittle finishes.

If it is simply to reduce the visible long term deflection, normally you would not prrecamber by more than the short term dead load deflection.

RE: Camber for two way slab

(OP)
I guess, what you ask, is actually part of my question. Why did "they" precamber the slab? Most likely just to have a flat condition at the start of live load application. This would be a similar case to using cambered owsj. As you noted, the cambering will have nil effect of finishes etc. and I think that this was not the reason "they" cambered the slab.

So you think that the immediate dead load deflection would be enough? Is this stated in a code that you know of?..Or some other reference text?

thanks
Dave

RE: Camber for two way slab

If you camber the slab then your depth when the slab is cast will be different in the middle than at the ends, at least until you have enough concrete in place to make up for this.  It seems like that would give them trouble in the field casting and finishing the slab and that you may lose some of your effective depth.  I don't have experience with this, but these problems come to mind.

RE: Camber for two way slab

Dave

Camber is not limited by any codes I know of. It's use is a "design/engineering judgement" decision, not something that needs to be limited by a code. Theoretically you can use any amount of camber you want as long as you maintain the deflected shape within the code limits at all times.

Having a flat condition at the time of application of live load is not a code judgement and is probably not achieveable unless you know the time of application of the live load and calculate deflections at that time due to the dead loads and long term effects. There is software that can do this for you But why would you want this?

The main use of precamber is to limit the long term visible deflection and ponding deflection on exposed slabs.

re the comment on thinner slabs, when precambering, the contractor should ensure that the slab thickness is maintained. Both the top and bottom surface of the member are supposed to be precambered. Simply precambering the bottom and maintaining a flat soffit is not logical.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources