INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

SPT borehole for line transmission

SPT borehole for line transmission

SPT borehole for line transmission

(OP)
In brazilian line transmission 238 or 500kV foundation design, we do not make one SPT borehole per tower but one per 500m moreless.
Tell me something of your experiences about, please.
Sorry for bad english!

RE: SPT borehole for line transmission

The number of site exploration depends of the project specification, the geotechnical engineer experience, data available from other projects in the vicinity and knowledge of the region.

You may have additional chance for specific response if you ask this question in the Transmission Structure Engineering, ( Forum608 )

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources