INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Bridge over Environmentally Sensitive Area

Bridge over Environmentally Sensitive Area

Bridge over Environmentally Sensitive Area

(OP)
I am looking for a type of bridge construction that minimizes impacts to a marshy area that will be crossed.  It will be a low-level (causeway type) structure, presumably on pile bents, with repetitive spans for approximately 1500' total length.  A "Top-Down" type of construction would be desireable.  Does anyone know of any projects where these considerations were a part of the design and construction?

RE: Bridge over Environmentally Sensitive Area

Depends on how much funding you have available, and your construction schedule.  You could do a "launched" type structure using precast elements, with a cased drilled shaft substructure; depends on soil conditions.

RE: Bridge over Environmentally Sensitive Area

One design used for this situation is cast-in-place flat slab (often 30 ft spans) supported by driven steel H-pile. Pile driving, falsework erection/wrecking, and concrete placement can be performed by one fairly small crane from the bridge deck. The H-pile cause minimal disturbance and the simple, repetitive formwork is reuseable.
Depending on conditions, it may be possible to accelerate the schedule by working the project from both ends and meeting in the middle.

RE: Bridge over Environmentally Sensitive Area

(OP)
Funding is limited, scheduling is open - County Project in FL.  I assume that construction will involve precast elements.  Anticipated sequencing: drive piles for bent ahead, install pile cap, install precast slabs (or precast beams w/CIP Deck), advance crane, repeat process.  This type of construction, I'm sure, has been done before.  What I'm looking for is a project(s) that have been built this way, to get some idea of costs, and to ID successful construction techniques and other considerations.  

RE: Bridge over Environmentally Sensitive Area

I have seen articles in the past on this. I think Civil Engineering had one a couple of years ago. In general, the piles were driven in front of the trestle, a pair of cap beams were installed and the deck placed. Spacing would be dependent on the crane - the larger the spacing, the heavier the crane, the stronger the deck. I would look at using timber piles to reduce cost, esp if lengths can be 60 ft or less. Timber piles will limit you to about 30-45 ton dependig on soil and pile size, but depending on bent spacing,that may not be a problem.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources