INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Hydro Power in Sewage Works

Hydro Power in Sewage Works

Hydro Power in Sewage Works

(OP)
We are looking into the feasibility of installing a small hydro electric unit downstream of a sewage inlet works.

The system will be around 250kW. It shall be a Kaplan type reaction turbine.

Although the sewage inlet works has screens(6mm 2 dimensions)and grit removal, I still have concerns regarding ragging up and grit erosion and build up in the turbine.

Does any one know of a similar installation, or have they considered one?

Thanks

Sow

RE: Hydro Power in Sewage Works

You have some very valid concerns...I just can't imagine the O&M on a facility like this...I have worked on several facilities that harness raw water from canals and that is in itself tough to handle and labor intensive.  Sewage...I can't imagine the grit being anywhere near friendly to accomodate.  Ragging..well, all this would have to be addressed most likely by an elaborate upgrade to the pre treatment to the headworks to make it work with any degree of consistency.

I am assuming the the influent tot he headworks in from a force main or some type of system under pressure?  Even then, I can't see there being that much energy available at the headworks to make this feasible.  What are your flows like before I go to far assuming?  And more importantly, what are your ideas and thoughts beyond the obvious you stated?  What would you use the power for, what is your target ROI?

Even with all that, it's still fun to think about...

BobPE

RE: Hydro Power in Sewage Works

If the source point of the sewerage has a sufficient head above the discharge point there is nothing technically against the power recovery by dropping in a Kaplan unit.

The erosion of the runner is obviously an issue but at 250kW the associated equipment and maintenance work may not be as viable as it looks.

I have seen several energy recovery systems for the coooling water circuits of power plants, using both seawater and river water, but for reasons they all came to a halt after additional investments for renewing the components were either ignored or could not be justified.  

Even at 250kw the civil and mechanical work arranagement have to allow for a outage of the kaplan and a bypass is therefore necessary with a system to dissipate the unwanted 250kw of energy. The capital cost of the transmission system, switch gears and operation and control for such a small unit have yet to be proven viable.

The erosion of the runner, which can be replaced easily, is the least of the above worries.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources