INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

service road replacement between two lakes

service road replacement between two lakes

service road replacement between two lakes

(OP)
I would like to ask some advice.  I have a project where I need to repair a roadway.  The roadway is in between two lakes with four culverts underneath.  There is always a pavement failure because the culverts are already corroded.  There is always a dip on the road and to bring it back to grade additional asphalt are placed on top of the existing road.  I would like to repair the road permanently.  I cannot place cofferdams upstream and downstream of the culvert since it will cause flooding on the upstream basin.  The existing culvert is corrugated metal pipe and I would like to replace it.  The pipe is approximately an 18-inch or 24 inch pipe.  
Is there a way that I can replace the culvert?  Upon replacement of the culvert I am planning to replace the limerock base with an asphalt base.  I would appreciate if you can provide any suggestions that you can provide to replace this culvert without constructing cofferdams?  Your input is greatly appreciated.

RE: service road replacement between two lakes

Excavate the road for pipe replace ment just to the side of the existing 'culverts'. Place small box culverts (3 x8)in the excavation with enough capacity to replace pipes. have the supplier design the boxes for the type of load required. Once the boxes are in place, backfill. Remove the corrugated pipes and backfill. Reshape the channels to meet the new boxes.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources