INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Michigan Fresh Air Requirements

Michigan Fresh Air Requirements

Michigan Fresh Air Requirements

(OP)
When dealing with the required amount of Fresh air a building must have, the size of the unit is getting astronomical. What ways can the fresh air requirements be meet and the HVAC equipment not be huge.

I have heard losely of taking 15% of the fresh air and sizing the unit, then just dampering in 85% unconditioned air to satisfy the requirement. Please help

RE: Michigan Fresh Air Requirements

A better way to meet the fresh air requirements, and not have 'huge' equipment is to consider some form of heat recovery. A heat wheel (for instance) will recover sensible and latent heat and reduce the amount of reheat (or recool) that your outdoor air requires.

Most of the major air handling companies have heat recovery options.

**If you are not part of the solution, then you are part of the precipitate.**

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources