INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Review Design Cost

Review Design Cost

Review Design Cost

(OP)
Add to cost of design and fabrication of many equipments (pressuere vessels by ASME code and fired heaters by API 560) to a refinery, We need know approach costing of following activities developed by our reperesentative (Purchaser's representive) on site, versus (%) total cost of equipments :

- Develop of each Job Instruction
- Contact to potential vendors and selction of best
- Review of calculations
- Review of technical drawings
- Visit to fabrication shop (if necessary)
- Control of fabricaction schedule
- Thecnical Review and received equipments on site

How is recommended to define fees and budget about?

RE: Review Design Cost

Estimate man-hours required for each task, and multiply by appropriate labor rate.

RE: Review Design Cost

Estimating the hours is a very sharp double-edged sword.  If you use a P10 case you'll get a lot of bids, and lose money on most of the.  With a P90 case you won't get as many bids, but you'll usually do pretty well on the ones you get.  Even with a P50 case you'll be under actuals half the time and over on the other half--with the real possibility of a bias that puts you over on the big projects and under on the small ones.  

I generally use a P75 case and accept that I won't get all the jobs I bid on, but I won't lose money on many that I do get (I say that on the very day I lost my shirt on a hard-dollar bid that I blew).

David Simpson, PE
MuleShoe Engineering
www.muleshoe-eng.com
Please see FAQ731-376 for tips on how to make the best use of Eng-Tips Fora.

The Plural of "anecdote" is not "data"

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources