Add to cost of design and fabrication of many equipments (pressuere vessels by ASME code and fired heaters by API 560) to a refinery, We need know approach costing of following activities developed by our reperesentative (Purchaser's representive) on site, versus (%) total cost of equipments :
- Develop of each Job Instruction
- Contact to potential vendors and selction of best
- Review of calculations
- Review of technical drawings
- Visit to fabrication shop (if necessary)
- Control of fabricaction schedule
- Thecnical Review and received equipments on site
How is recommended to define fees and budget about?
- Develop of each Job Instruction
- Contact to potential vendors and selction of best
- Review of calculations
- Review of technical drawings
- Visit to fabrication shop (if necessary)
- Control of fabricaction schedule
- Thecnical Review and received equipments on site
How is recommended to define fees and budget about?





RE: Review Design Cost
RE: Review Design Cost
I generally use a P75 case and accept that I won't get all the jobs I bid on, but I won't lose money on many that I do get (I say that on the very day I lost my shirt on a hard-dollar bid that I blew).
David Simpson, PE
MuleShoe Engineering
www.muleshoe-eng.com