INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Post Tension Newbie
3

Post Tension Newbie

Post Tension Newbie

(OP)
Hi folks,

I'm doing some post tension design for the first time and I have a question about something that a coworker mentioned to me.  According to our notes and specs, we basically provide the effective tensile load required for the beam to operate.  Losses, anchorages and other items are for the manufacturer to check and design.  In addition to the PT design, I have been instructed to design the beam to include enough mild steel (bonded) for a special condition which includes the dead load and 25% of the live load. This will allow the beam to act like a regular (non-PT) beam and support itself if something should happen to the cables.  I have searched through the codes, but have not yet found a reference to this requirement.  Could someone please let me know if you are familiar with this stipulation?  I am having to add a lot of mild steel and I believe I will need to do some additional calcs to make sure the beam is still acceptable. Thanks in advance for any help or advice you can offer.

RE: Post Tension Newbie

Hi bevo98,

I have not heard of such a method when designing post-tensioned.  Post-tensioning, prestresses a beam and no amount of mild reinforcing for a given depth of beam can measure up to such a post-tensioned capacity.

I don't know what industry you are in, but from my experience I have had to design all my prestressed or cast-in-place post-tensioned members.

Regards

VOD

RE: Post Tension Newbie

2
The 100% dead + 25% live requirement was a modification to ACI-318 by the Uniform Building Code.  See 1997 UBC Section 1918.9.2.2. It is not required by the International Building Code.

RE: Post Tension Newbie

(OP)
BAM!!!

Now that's some good information.

Thanks Taro

RE: Post Tension Newbie

My p-t background is in bridges, my apologies for not being helpful.

Regards

VOD

RE: Post Tension Newbie

VOD - nothing to apologize about - Eng-Tips runs on enthusiasm and participation.   Appreciate all your posts.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources