How to move the whole schedule?
How to move the whole schedule?
(OP)
Hi,
Is it possible (and if yes - how?) to move the whole schedule in MS Project without changing durations of any tasks. Let's say we create a project that would end on December 15 and it would take 6 weeks to complete all of its tasks (often linked). Now we want to move the completion date to December 1, moving the start date also as well as all the tasks at once. Can this be done?
Thank you,
Oxana
Is it possible (and if yes - how?) to move the whole schedule in MS Project without changing durations of any tasks. Let's say we create a project that would end on December 15 and it would take 6 weeks to complete all of its tasks (often linked). Now we want to move the completion date to December 1, moving the start date also as well as all the tasks at once. Can this be done?
Thank you,
Oxana





RE: How to move the whole schedule?
You can change the project start date in the menu selection
Project|Project Information
TTFN
RE: How to move the whole schedule?
RE: How to move the whole schedule?
Also you say that is greyed out?... like if it were only showing the baseline... Check for constraints and if that doesn't work, let me see the file.
SANTO.
RE: How to move the whole schedule?
RE: How to move the whole schedule?
i.e you have project that started on 01/01/04 and there is a repeat starting 01/01/05.
to get there:
Go to "view" - "Toolbars" - "Analysis"
There will now be a new tool bar.
Press Adjust dates.
And the rest is straight foreward.
You can change the date backward
Cheers
Blooda