INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Wood Frame Building, MWFRS or Componet?
2

Wood Frame Building, MWFRS or Componet?

Wood Frame Building, MWFRS or Componet?

(OP)
Under the IBC2000 (or ASCE-7), for a rectangular, single story, wood frame building with a manufactured wood truss roof, I maintain that the wood studs and the wood trusses are the Main WindForce Resisting System.  They should be evaluated using the Wind Loads for MWFRS, not Components.  

When evaluating, siding, roof sheathing, door and window headers or jambs for wind loads, they would be evaluated using the Wind Loads for Components.

Do you forum members agree or disagree and why?

RE: Wood Frame Building, MWFRS or Componet?

If a member is part of a system that provides lateral load resistance for the building it is MWFRS.  Keep in mind that a member may be designed with both C&C and MWFRS depending on the load.  Wood trusses are not MW.  They hold up a couple feet of roof, they do not provide stability or lateral resistance to the building as a whole.  The same goes for wood studs loaded out-of-plane for bending.  

Sheathing is C&C for out-of-plane loads and MW when it acts in-plane as part of a shearwall or roof diaphragm.  The same goes for masonry rebar: same concept different material.  Steel deck is like sheathing, C&C out of plane, MW in plane as a diaphragm.  Moment frames supporting a diapragm are MW.  Headers, jambs, C&C.  Footings are also important.  Shearwall footings and Moment or braced frame footings are probably MWFRS.  Otherwise, they are C&C depending on tributary area.

If a member has a very large tributary area the MWFRS loads may be appropriate.

There is another similar thread in Struct. Eng. Other topics called "Components and Cladding Wind loads", currently page 2.  Check it out for more stuff.  These are my opinions as I understand them based on my judgment and talking to some other engineers around my area.  I hope some of it helps! :)

RE: Wood Frame Building, MWFRS or Componet?

(OP)
UcfSE:

Thanks for the noting the other thread, it actually states the question better than I did.  I'll follow up there.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources