INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Changing Schedule Variance calculation

Changing Schedule Variance calculation

Changing Schedule Variance calculation

(OP)
I need to display schedule slip calculated in calendar days. My project calendar is set up in work days (5 day weeks, 8 hour days).

Is there a way to display slip in calendar days on the table portion of the GANTT view? I have used the "Schedule Varience" selection, but the calculation is apparently based on the 5-day work schedule associated with the project.

RE: Changing Schedule Variance calculation

TO get a calendar day duratio instead of a working day duration I use elapsed days, put an "e" in front of the duration units. You might be able to use this in some way, I haven't tried it but I thought it might be useful.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources