INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Reviewing changes in MS Project

Reviewing changes in MS Project

Reviewing changes in MS Project

(OP)
We are using MS Project to review and and schedule resources for on going projects. Weekly we update projected start dates as well as other critical information. Is there any way that when a change is made to a task it can be tracked? Others not present at the weekly updates need to see any changes made.

Thank you.

RE: Reviewing changes in MS Project

Doesn't baselining before making the change do what you want?

TTFN

RE: Reviewing changes in MS Project

(OP)
Unfortunately baselining only tracks changes to start date and completion date. If there is a way for it to tack custom fields I am unaware of it. Can it do this?

Thank you

RE: Reviewing changes in MS Project

Probably not within Project itself.  There are no provisions to track changes to text, etc.  You'd have to export those fields to something like Word

TTFN

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources